Primary Injection Test Set is used for loading calibration and testing of CT's bi-metals relays, protection relays, etc. Mostly this unit is designed as per customer's specification. This test set is of 15 minutes ON/30 Minutes OFF duty i.e. testing duty only. Loading transformers are design for continuous use for temperature rise for bus duct/bus bar, etc.
Features
Compact in nature
It is available in portable trolley type/stationery type model Amps
Optional digital/analogue timer
Main Transformer up to 25,000 Amps Naturally air-cooled type
Technical Specifications
Step Down Transformer: A double wound transformer is used for supplying high current at low voltage for testing
Current Control: A step-less Auto Transformer is used for controlling output current from Zero to Maximum
Input Voltage Ranges: 230/415 Volts single/two/three phase 50Hz. AC supply
Output Voltage Ranges: As per requirement
Output Current: Up to 25000 Amps
Capacity: Up to 500 KVA
Duty: 15 Minutes ON-30 Minutes OFF in case of Primary Injection test set and continuous in case of Loading Transformer
Metering: Multi range Ampere meter of class 1.5 with CT of class 0.5 are provided on secondary side to indicate output current
Protection: ON-OFF Switch with fuse is provided to protect the unit against short circuit, push button to actual and cut of output
Housing: Each unit is housed in a MS sheet body, supported with angle iron frame. The oil-cooled models are housed in suitable MS tank and the control panel is on the tank or as per requiems
Optional: (a) Voltmeter (b) Timer as per requirement (c) Rubber cable (c) Zero start interlocking with by pass switch
Termination: The output is brought out on suitable Bus Bar/Terminals.